Under a Guaranteed Maximum Price (GMP) contract, what happens when actual project costs fall below the GMP?
-
A
The owner retains all savings
-
B
Savings are typically shared between owner and contractor per a agreed ratio
-
C
The contractor keeps all savings as additional profit
-
D
The GMP is retroactively reduced for future projects