A contractor submits a claim for extended general conditions costs due to an owner-caused delay. Which document is most critical for the auditor to review first?
-
A
The contractor's profit and loss statement
-
B
The project schedule showing the critical path and delay impact
-
C
The contractor's bank statements
-
D
The surety bond terms and conditions