When auditing a construction project's contingency reserve, an auditor should verify that the reserve is:
-
A
Included in the contractor's profit margin
-
B
Separately identified and subject to owner approval for use
-
C
Distributed equally across all work packages
-
D
Allocated only to subcontractors