  1. When auditing a construction project's contingency reserve, an auditor should verify that the reserve is:

    Answer: Separately identified and subject to owner approval for use

    Contingency reserves should be explicitly tracked and require owner authorization before drawdown to prevent unauthorized spending.

  2. Which internal control helps prevent a project manager from approving their own invoices on a construction project?

    Answer: Dual-signature requirement for payments

    Requiring two authorized signatures on payment approvals ensures no single individual can unilaterally approve their own expenditures.

  3. An auditor finds that a construction project's work breakdown structure (WBS) does not align with its cost codes. This discrepancy most likely impairs:

    Answer: Accurate cost tracking and performance measurement

    Misalignment between the WBS and cost codes makes it impossible to accurately track costs by work package and measure performance.

  4. In construction project auditing, a 'look-ahead schedule' is primarily reviewed to assess:

    Answer: Near-term work planning and resource availability

    A look-ahead schedule (typically 3–6 weeks) documents near-term work plans and reveals whether resources and materials are being properly coordinated.

  5. Which variance threshold trigger should a construction auditor recommend as a best practice for mandatory management reporting?

    Answer: Variances exceeding 5–10% of budget or a defined dollar threshold

    A percentage or dollar threshold (commonly 5–10%) ensures significant variances receive management attention without creating noise from minor fluctuations.

  6. A construction project auditor detects that baseline schedules have been revised multiple times without documented owner approval. This is an indicator of:

    Answer: Unauthorized schedule manipulation

    Repeated baseline revisions without owner approval may hide schedule slippage and distort performance metrics.