CCA Construction Project Management and Controls Flashcards
6 cards from real CCA practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 6 CCA Construction Project Management and Controls flashcards as text
A construction auditor identifies that a contractor submitted invoices for materials that were never delivered to the job site. This finding most directly indicates a failure in which control?
Answer: Receiving and inspection controls
Receiving and inspection controls require physical verification that materials are delivered and accepted before payment is authorized.
Which metric is most useful for a CCA auditor assessing whether a construction project's costs are trending toward overrun?
Answer: Estimate at Completion (EAC)
The Estimate at Completion forecasts the total final cost based on current performance trends, alerting auditors to potential overruns before they fully materialize.
When reviewing construction project schedules, an auditor should be alert to schedule compression techniques that may increase which project risk?
Answer: Quality defects and rework costs
Crashing or fast-tracking schedules often leads to concurrent work and reduced quality oversight, increasing defect rates and costly rework.
An auditor reviewing project closeout documentation would verify that punch list items are resolved before approving which payment?
Answer: Final payment and release of retention
Final payment and retention release are contingent on completion of all punch list items, ensuring the owner does not pay for incomplete or defective work.
Which internal control best prevents a contractor from double-billing labor hours on multiple cost codes for the same workers?
Answer: Reconciliation of certified payroll records to labor cost distribution reports
Certified payroll records list actual hours and wages per worker, and reconciling these to cost distribution reports exposes duplicate labor charges across cost codes.
A CCA auditor finds that change orders consistently increase scope but the project schedule was never formally updated. What risk does this create?
Answer: Inability to accurately assess contractor time extension entitlements or delay damages
Without schedule updates reflecting added scope, it becomes impossible to fairly evaluate contractor delay claims or determine concurrent delay situations.