CCA Change Orders and Claims Management Flashcards
6 cards from real CCA practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 6 CCA Change Orders and Claims Management flashcards as text
Under a lump sum construction contract, which condition typically gives a contractor the right to submit a change order request?
Answer: Owner-directed changes to the original project scope
Change orders under lump sum contracts are triggered by owner-directed scope changes, differing site conditions, or other contract-specified events beyond the contractor's control.
Which document provides the auditor with the strongest evidence that a change order price was fair and reasonable?
Answer: Independent cost estimate prepared before the change order was negotiated
An independent cost estimate prepared prior to negotiation gives the auditor a benchmark against which to assess whether the final negotiated price was reasonable.
A construction auditor reviewing change order patterns finds that 40% of all change orders involve work that was arguably within the original contract scope. This is called:
Answer: Scope creep through change order misuse
Submitting change orders for work already included in the original contract scope is a common contractor tactic to recover additional profit on work they are already obligated to perform.
What is a constructive change in construction contract auditing?
Answer: An owner action or inaction that forces the contractor to perform extra work without a formal change order
Constructive changes occur when owner conduct such as over-inspection, changed interpretations, or access restrictions effectively orders extra work without issuing a formal change order.
When auditing change order markups for overhead and profit, what should the auditor compare the contractor's claimed markup against?
Answer: The markup rates specified in the original contract
Most construction contracts specify allowable overhead and profit markup percentages for change orders; these contractual rates are the auditor's primary benchmark.
An auditor reviewing a construction claim finds the contractor submitted a Total Cost claim. What is the primary weakness of this claim method?
Answer: It assumes all cost overruns are the owner's responsibility without isolating specific causes
Total Cost claims compare bid cost to actual cost and blame all overruns on the owner, ignoring the contractor's own inefficiencies, estimating errors, or subcontractor failures.