Which change order review step is most critical for detecting inflated material costs submitted by a contractor?
-
A
Comparing supplier invoices to the amounts billed in the change order
-
B
Reviewing the contractor's insurance certificates
-
C
Confirming the change order was signed by the project manager
-
D
Verifying that the change order number is sequential