In a Critical Path Method (CPM) schedule, what is total float?
-
A
The total duration of all activities on the critical path
-
B
The time an activity can be delayed without delaying the next activity's early start
-
C
The buffer added by the owner to the contract completion date
-
D
The time an activity can be delayed without delaying project completion