What does the Cost Performance Index (CPI) measure in Earned Value Management?
-
A
The ratio of Earned Value to Actual Cost incurred
-
B
The ratio of Actual Cost to the original budget
-
C
The total cost variance across all project phases
-
D
The forecasted total cost at project completion