During a bathroom renovation, the client requests a change to the tile selection after the order has been placed. What is the BEST first step for the designer?
-
A
Cancel the original order immediately
-
B
Issue a formal change order documenting the request, cost impact, and schedule impact
-
C
Verbally agree and proceed with the new selection
-
D
Inform the contractor without notifying the client of cost changes