A client changes the scope of an AV installation mid-project by adding 12 additional ceiling speakers. What is the FIRST step a CAT should take?
-
A
Begin installing the additional speakers immediately
-
B
Issue a formal change order documenting added cost and timeline impact
-
C
Refuse the request until the original scope is complete
-
D
Inform the general contractor verbally and proceed