CAT Project and Client Management 2 — Questions and Answers
Question 1: A client changes the scope of an AV installation mid-project by adding 12 additional ceiling speakers. What is the FIRST step a CAT should take?
- Begin installing the additional speakers immediately
- Issue a formal change order documenting added cost and timeline impact (Correct answer)
- Refuse the request until the original scope is complete
- Inform the general contractor verbally and proceed
Correct answer: Issue a formal change order documenting added cost and timeline impact
A formal change order protects both parties by documenting scope changes, revised costs, and updated timelines before work begins.
Question 2: Which document establishes the agreed-upon deliverables, schedule, and payment terms for a commercial AV project?
- RFI (Request for Information)
- As-built drawing
- Contract/Statement of Work (Correct answer)
- Punch list
Correct answer: Contract/Statement of Work
A contract or Statement of Work defines deliverables, schedule, and payment terms and is the binding agreement between client and contractor.
Question 3: During a site walkthrough for a new boardroom AV system, you discover the ceiling height is 2 feet lower than shown on the architect's drawings. What should you do?
- Adjust your design without notifying the client
- Submit an RFI to the architect to resolve the discrepancy (Correct answer)
- Cancel the project until drawings are corrected
- Proceed based on your field measurements and ignore the drawings
Correct answer: Submit an RFI to the architect to resolve the discrepancy
An RFI formally documents discrepancies between drawings and field conditions so the design team can issue corrected documentation.
Question 4: A commercial AV project has a hard opening deadline for a hotel grand ballroom. Which scheduling tool is MOST useful for identifying tasks that cannot be delayed without pushing the completion date?
- Gantt chart only
- Critical path method (CPM) (Correct answer)
- Budget spreadsheet
- Daily punch list
Correct answer: Critical path method (CPM)
The critical path method identifies the sequence of dependent tasks whose delay would directly extend the overall project duration.
Question 5: A client requests a system demonstration before final payment is released. This review is BEST described as:
- Substantial completion walkthrough
- System acceptance testing (SAT) (Correct answer)
- Pre-bid meeting
- Design development review
Correct answer: System acceptance testing (SAT)
System acceptance testing (SAT) is a formal client verification that the installed system meets specified performance requirements before final payment.
Question 6: When budgeting a large commercial AV installation, a contingency percentage is typically added to cover:
- Profit margin above the base bid
- Unforeseen conditions and scope uncertainties (Correct answer)
- Labor overtime only
- Equipment warranty costs
Correct answer: Unforeseen conditions and scope uncertainties
Contingency funds are reserved for unforeseen conditions, design changes, or scope uncertainties that arise during construction.
Question 7: A subcontractor on your AV project consistently submits invoices late, causing delays in your billing cycle. The BEST corrective action is to:
- Pay the subcontractor without invoices to keep the project moving
- Add invoice submission deadlines to the subcontract agreement (Correct answer)
- Replace the subcontractor immediately
- Absorb the billing delays without documentation
Correct answer: Add invoice submission deadlines to the subcontract agreement
Formalizing invoice submission deadlines in the subcontract agreement creates enforceable terms that protect cash flow and billing timelines.
A client changes the scope of an AV installation mid-project by adding 12 additional ceiling speakers.
What is the FIRST step a CAT should take?