Risk-Based Testing Strategies Flashcards

6 cards from real CAST practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 6 Risk-Based Testing Strategies flashcards as text
  1. In a risk-based testing strategy, which two factors are primarily used to assess and prioritize risks?

    Answer: Likelihood of failure and impact of failure

    Risk-based testing prioritizes testing efforts based on the potential risk of failure and the impact that failure would have on the business or users. The combination of likelihood (probability) and impact (severity) determines the overall risk level, guiding the test strategy.

  2. A project team is developing a new e-commerce application. They have limited time for testing before the scheduled launch. Using a risk-based approach, which module should receive the HIGHEST priority for testing?

    Answer: The payment processing and checkout gateway

    The payment processing and checkout gateway represents the highest risk. A failure in this area would have a direct and severe financial impact on the business and would critically affect the user's primary goal. While other features are important, a failure in payment processing is the most impactful potential failure.

  3. Which of the following is the primary goal of implementing a risk-based testing strategy?

    Answer: To optimize testing efforts by focusing on the most critical areas.

    The fundamental purpose of risk-based testing is not to test everything exhaustively, but to allocate limited testing resources (time, people, budget) to the parts of the application that pose the greatest risk to the project's success. This ensures that the most critical potential issues are addressed first.

  4. During the risk identification phase of risk-based testing, which activity is LEAST likely to be performed?

    Answer: Writing and executing all high-priority test cases.

    Writing and executing test cases is part of the test execution phase, which happens *after* risks have been identified, analyzed, and a test plan has been created. The risk identification phase focuses on discovering potential problems through activities like meetings, data analysis, and requirements review.

  5. A feature is identified as having a high probability of failure but a very low business impact if it fails. According to a typical risk-based testing strategy, how should testing for this feature be prioritized?

    Answer: It should be prioritized lower than high-impact features.

    In risk-based testing, the impact of a failure is a critical component of prioritization. Even if a failure is likely, if its impact is negligible, it represents a lower overall risk than a feature with a lower probability of failure but a critical impact. Therefore, it should be prioritized below high-impact items.

  6. What is the main output of the risk analysis and prioritization process in risk-based testing?

    Answer: A prioritized list of risks that informs the test plan and strategy.

    After identifying and analyzing risks (assessing their likelihood and impact), the key outcome is a ranked list of risks. This prioritized list serves as the foundation for the test plan, dictating which areas will be tested most intensively, in what order, and with what resources.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. seo.nlx.org — Passing score, time limit · verified Oct 2026
  2. pge.com — Retake policy · verified Oct 2026
  3. eei.org — Test delivery, eligibility, score release, score validity · verified Oct 2026