Question 1: A high-power, low-interest stakeholder is identified on a project. According to the power/interest grid, what is the recommended engagement strategy?
- Manage closely
- Monitor with minimal effort
- Keep satisfied (Correct answer)
- Keep informed
Correct answer: Keep satisfied
High-power, low-interest stakeholders should be kept satisfied to prevent them from becoming blockers, without over-engaging them.
Question 2: Which document describes how stakeholders will be identified, analyzed, and engaged throughout the project?
- Project charter
- Stakeholder register
- Stakeholder engagement plan (Correct answer)
- Communications management plan
Correct answer: Stakeholder engagement plan
The stakeholder engagement plan defines the strategies and actions required to promote stakeholder involvement aligned with their needs and project objectives.
Question 3: A project manager uses workshops to build consensus among conflicting stakeholders. This technique BEST represents which approach?
- Inform
- Monitor
- Collaborate (Correct answer)
- Restrict
Correct answer: Collaborate
Facilitated workshops bring stakeholders together to resolve differences and reach consensus, which exemplifies the collaborate engagement approach.
Question 4: During project closure, a project manager documents lessons learned about stakeholder engagement. Where are these lessons PRIMARILY stored?
- Stakeholder register
- Project charter
- Lessons learned register (Correct answer)
- Issue log
Correct answer: Lessons learned register
Lessons learned about stakeholder engagement are captured in the lessons learned register and become part of organizational process assets for future projects.
Question 5: A project manager receives conflicting requirements from two equally powerful stakeholders. What is the BEST first step?
- Choose the requirement that is easier to implement
- Escalate immediately to the project sponsor
- Facilitate a meeting between the stakeholders to reach agreement (Correct answer)
- Ignore the conflict and proceed with both requirements
Correct answer: Facilitate a meeting between the stakeholders to reach agreement
Facilitating direct discussion between conflicting stakeholders to reach mutual agreement is the most effective first step before escalation.
Question 6: What is the PRIMARY purpose of an issue log in the context of stakeholder management?
- Track project budget variances
- Document stakeholder concerns and track their resolution (Correct answer)
- Record team member performance
- List approved change requests
Correct answer: Document stakeholder concerns and track their resolution
The issue log records stakeholder concerns, conflicts, and problems along with their status and resolution actions to ensure nothing is overlooked.
Question 7: Which of the following BEST describes 'unaware' stakeholders in the engagement matrix?
- They know about the project but are indifferent
- They do not know about the project or its potential impact on them (Correct answer)
- They actively oppose the project
- They support the project without being involved
Correct answer: They do not know about the project or its potential impact on them
Unaware stakeholders lack knowledge about the project and therefore cannot assess its impact on their interests.
A high-power, low-interest stakeholder is identified on a project.
According to the power/interest grid, what is the recommended engagement strategy?