A project manager discovers a powerful stakeholder who was not included in the stakeholder register. What should be done first?
-
A
Close the project and restart planning
-
B
Add the stakeholder to the register and assess their influence
-
C
Ignore them if the project is already underway
-
D
Remove a less important stakeholder to balance the register