What is the PRIMARY purpose of a Work Breakdown Structure (WBS)?
-
A
To assign responsibilities to team members for each activity
-
B
To decompose total project scope into smaller, manageable components
-
C
To sequence project activities and determine their dependencies
-
D
To estimate durations for all project tasks