CAPM Project Management Framework 4 — Questions and Answers
Question 1: What is the PRIMARY purpose of a Work Breakdown Structure (WBS)?
- To assign responsibilities to team members for each activity
- To decompose total project scope into smaller, manageable components (Correct answer)
- To sequence project activities and determine their dependencies
- To estimate durations for all project tasks
Correct answer: To decompose total project scope into smaller, manageable components
The WBS decomposes the total scope of the project into smaller, more manageable work packages to facilitate planning and control.
Question 2: Stakeholder identification should FIRST occur during which process group?
- Planning
- Executing
- Initiating (Correct answer)
- Monitoring and Controlling
Correct answer: Initiating
Stakeholder identification is part of the Initiating process group and should be done as early as possible to engage stakeholders throughout the project.
Question 3: Which term describes work that is included in a project but was not authorized or planned, negatively affecting the schedule and cost?
- Gold plating
- Scope creep (Correct answer)
- Rework
- Progressive elaboration
Correct answer: Scope creep
Scope creep refers to uncontrolled expansion of project scope without corresponding adjustments to time, cost, and resources.
Question 4: A CAPM candidate reads that a project has a Cost Performance Index (CPI) of 0.85. What does this mean?
- The project is getting $1.00 worth of work for every $0.85 spent
- The project is getting $0.85 worth of work for every $1.00 spent (Correct answer)
- The project is 85% complete
- The project is 15% over schedule
Correct answer: The project is getting $0.85 worth of work for every $1.00 spent
A CPI of 0.85 means the project is only receiving $0.85 worth of value for each $1.00 spent, indicating a cost overrun.
Question 5: Which of the following BEST describes progressive elaboration in project management?
- Breaking the WBS into smaller and smaller detail until work packages are reached
- Continuously improving and detailing a project plan as more information becomes available (Correct answer)
- Assigning increasing levels of risk to activities as the project progresses
- Escalating project issues to higher management as they become more serious
Correct answer: Continuously improving and detailing a project plan as more information becomes available
Progressive elaboration means that planning is done in increasing detail as more information and greater accuracy becomes available throughout the project.
Question 6: A project manager is selecting between two risk response strategies. One eliminates the threat entirely; the other reduces its probability. Which terms match these strategies?
- Mitigate and Accept
- Transfer and Avoid
- Avoid and Mitigate (Correct answer)
- Exploit and Enhance
Correct answer: Avoid and Mitigate
Avoid eliminates the threat entirely by changing the plan, while Mitigate reduces the probability or impact of the risk to an acceptable level.
Question 7: The project management plan differs from project documents in that the project management plan:
- Is updated more frequently than project documents
- Is a single, approved document that guides project execution and control (Correct answer)
- Contains only the schedule baseline and cost baseline
- Is owned by the project sponsor, not the project manager
Correct answer: Is a single, approved document that guides project execution and control
The project management plan is the approved, integrated document that describes how the project will be executed, monitored, and controlled.