A stakeholder requests information that was not planned in the communications management plan. The project manager should FIRST:
-
A
Provide the information immediately to satisfy the stakeholder
-
B
Ignore the request as it is outside the plan
-
C
Evaluate the request and update the communications management plan if warranted
-
D
Escalate the request to the project sponsor