CAPM Predictive Methodologies 3 — Questions and Answers
Question 1: Which predictive scheduling technique calculates early start, early finish, late start, and late finish dates for each activity?
- Resource leveling
- Critical Path Method (Correct answer)
- Monte Carlo simulation
- Parametric estimating
Correct answer: Critical Path Method
The Critical Path Method (CPM) performs forward and backward passes to calculate the four dates and identify float for each activity.
Question 2: In predictive project management, what is the purpose of a Configuration Management System?
- Track team member performance
- Control changes to project deliverables and documentation (Correct answer)
- Manage vendor contracts
- Monitor project risks
Correct answer: Control changes to project deliverables and documentation
Configuration Management Systems track and control changes to product characteristics, ensuring only approved changes are implemented.
Question 3: A project manager is creating a RACI chart. What does the 'A' stand for?
- Available
- Accountable (Correct answer)
- Assigned
- Authorized
Correct answer: Accountable
In a RACI chart, 'A' stands for Accountable — the single person who is ultimately answerable for the correct completion of the task.
Question 4: Which type of cost estimate in predictive projects is typically the most accurate?
- Rough Order of Magnitude (ROM)
- Analogous estimate
- Parametric estimate
- Bottom-up estimate (Correct answer)
Correct answer: Bottom-up estimate
Bottom-up estimating aggregates estimates for individual work packages and is the most accurate but also most time-consuming technique.
Question 5: In a predictive lifecycle, scope changes after the baseline is set must go through which process?
- Risk management
- Integrated Change Control (Correct answer)
- Quality assurance
- Procurement planning
Correct answer: Integrated Change Control
All scope changes after baselining must be submitted as change requests and reviewed through Perform Integrated Change Control.
Question 6: A project team is using a fishbone diagram during a quality management meeting. What is its primary purpose?
- Track project milestones
- Identify root causes of a defect or problem (Correct answer)
- Display project schedule
- Assign team responsibilities
Correct answer: Identify root causes of a defect or problem
A fishbone (Ishikawa or cause-and-effect) diagram visually maps potential causes of a problem to identify root causes.
Question 7: Which predictive document links each requirement to its source and traces it through the project lifecycle?
- Scope Management Plan
- Requirements Traceability Matrix (Correct answer)
- Project Charter
- Work Breakdown Structure
Correct answer: Requirements Traceability Matrix
The Requirements Traceability Matrix links requirements from origin through design, build, and testing to ensure all are addressed.
Which predictive scheduling technique calculates early start, early finish, late start, and late finish dates for each activity?