  1. Which predictive scheduling technique calculates early start, early finish, late start, and late finish dates for each activity?

    Answer: Critical Path Method

    The Critical Path Method (CPM) performs forward and backward passes to calculate the four dates and identify float for each activity.

  2. In predictive project management, what is the purpose of a Configuration Management System?

    Answer: Control changes to project deliverables and documentation

    Configuration Management Systems track and control changes to product characteristics, ensuring only approved changes are implemented.

  3. A project manager is creating a RACI chart. What does the 'A' stand for?

    Answer: Accountable

    In a RACI chart, 'A' stands for Accountable — the single person who is ultimately answerable for the correct completion of the task.

  4. Which type of cost estimate in predictive projects is typically the most accurate?

    Answer: Bottom-up estimate

    Bottom-up estimating aggregates estimates for individual work packages and is the most accurate but also most time-consuming technique.

  5. In a predictive lifecycle, scope changes after the baseline is set must go through which process?

    Answer: Integrated Change Control

    All scope changes after baselining must be submitted as change requests and reviewed through Perform Integrated Change Control.

  6. A project team is using a fishbone diagram during a quality management meeting. What is its primary purpose?

    Answer: Identify root causes of a defect or problem

    A fishbone (Ishikawa or cause-and-effect) diagram visually maps potential causes of a problem to identify root causes.

  7. Which predictive document links each requirement to its source and traces it through the project lifecycle?

    Answer: Requirements Traceability Matrix

    The Requirements Traceability Matrix links requirements from origin through design, build, and testing to ensure all are addressed.