A project manager notices the CPI has been consistently 0.80 for the past three reporting periods. Using the EAC = BAC / CPI formula, what assumption is being made?
-
A
Future work will be at budgeted rates
-
B
The remaining work has zero cost
-
C
Current efficiency will continue throughout the project
-
D
The project scope will be reduced