CAPM Cost Management 5 — Questions and Answers
Question 1: A project manager notices the CPI has been consistently 0.80 for the past three reporting periods. Using the EAC = BAC / CPI formula, what assumption is being made?
- Future work will be at budgeted rates
- The remaining work has zero cost
- Current efficiency will continue throughout the project (Correct answer)
- The project scope will be reduced
Correct answer: Current efficiency will continue throughout the project
EAC = BAC / CPI assumes current cost efficiency (CPI) will persist for all remaining work on the project.
Question 2: What is the formula for Variance at Completion (VAC)?
- VAC = EAC - BAC
- VAC = BAC - EAC (Correct answer)
- VAC = EV - AC
- VAC = PV - EV
Correct answer: VAC = BAC - EAC
VAC = BAC - EAC; a positive VAC indicates the project will finish under budget, while negative means over budget.
Question 3: In the cost management plan, the level of precision refers to:
- The number of decimal places used in cost estimates
- The rounding rules applied to cost estimates (Correct answer)
- The frequency of cost reporting
- The tools used to develop cost estimates
Correct answer: The rounding rules applied to cost estimates
Level of precision defines the rounding convention for activity cost estimates, such as rounding to the nearest dollar or thousand.
Question 4: A project manager is asked to provide a rough order of magnitude (ROM) estimate. What accuracy range is typically associated with ROM estimates?
- -5% to +10%
- -10% to +25%
- -25% to +75% (Correct answer)
- -50% to +100%
Correct answer: -25% to +75%
ROM estimates typically have an accuracy range of -25% to +75%, as they are prepared early with limited information.
Question 5: Which document formally authorizes the project manager to apply organizational resources and includes a summary-level budget?
- Project management plan
- Project charter (Correct answer)
- Cost management plan
- Scope baseline
Correct answer: Project charter
The project charter authorizes the project, names the project manager, and includes a summary budget.
Question 6: When a project finishes with AC = $95,000 and BAC = $100,000, and EV = $100,000, what is the final Cost Variance?
- -$5,000
- +$5,000 (Correct answer)
- $0
- $100,000
Correct answer: +$5,000
CV = EV - AC = $100,000 - $95,000 = +$5,000, meaning the project finished $5,000 under budget.
Question 7: Life cycle costing is a technique that considers:
- Only the project's development costs
- Only the operational costs after deployment
- The total cost of ownership including development, operation, and disposal (Correct answer)
- The cost of each phase as a percentage of the total budget
Correct answer: The total cost of ownership including development, operation, and disposal
Life cycle costing evaluates total cost of ownership across the entire product life cycle, including acquisition, operation, maintenance, and disposal.
A project manager notices the CPI has been consistently 0.80 for the past three reporting periods.
Using the EAC = BAC / CPI formula, what assumption is being made?