Cost Management Flashcards
7 cards from real CAPM practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 7 Cost Management flashcards as text
A project manager notices the CPI has been consistently 0.80 for the past three reporting periods. Using the EAC = BAC / CPI formula, what assumption is being made?
Answer: Current efficiency will continue throughout the project
EAC = BAC / CPI assumes current cost efficiency (CPI) will persist for all remaining work on the project.
What is the formula for Variance at Completion (VAC)?
Answer: VAC = BAC - EAC
VAC = BAC - EAC; a positive VAC indicates the project will finish under budget, while negative means over budget.
In the cost management plan, the level of precision refers to:
Answer: The rounding rules applied to cost estimates
Level of precision defines the rounding convention for activity cost estimates, such as rounding to the nearest dollar or thousand.
A project manager is asked to provide a rough order of magnitude (ROM) estimate. What accuracy range is typically associated with ROM estimates?
Answer: -25% to +75%
ROM estimates typically have an accuracy range of -25% to +75%, as they are prepared early with limited information.
Which document formally authorizes the project manager to apply organizational resources and includes a summary-level budget?
Answer: Project charter
The project charter authorizes the project, names the project manager, and includes a summary budget.
When a project finishes with AC = $95,000 and BAC = $100,000, and EV = $100,000, what is the final Cost Variance?
Answer: +$5,000
CV = EV - AC = $100,000 - $95,000 = +$5,000, meaning the project finished $5,000 under budget.
Life cycle costing is a technique that considers:
Answer: The total cost of ownership including development, operation, and disposal
Life cycle costing evaluates total cost of ownership across the entire product life cycle, including acquisition, operation, maintenance, and disposal.