A project manager discovers that two key stakeholders have conflicting expectations about the project scope. What should the PM do FIRST?
-
A
Escalate the conflict to the project sponsor
-
B
Schedule a joint meeting to facilitate alignment between stakeholders
-
C
Update the project charter to reflect both expectations
-
D
Ignore minor conflicts and proceed with the original scope