A project manager is closing out a project phase. Which change control activity is MOST important before moving to the next phase?
-
A
Submitting all pending change requests to the sponsor
-
B
Verifying that all approved changes have been implemented and baselines are updated
-
C
Cancelling all open change requests
-
D
Transferring the change log to the operations team