A sponsor requests an urgent feature addition without going through the change control process. What should the project manager do?
-
A
Implement the change immediately since the sponsor approved it
-
B
Explain that all changes must follow the formal change control process
-
C
Escalate to senior management
-
D
Reject the change outright