CAPM Change Control & Configuration 3 — Questions and Answers
Question 1: A sponsor requests an urgent feature addition without going through the change control process. What should the project manager do?
- Implement the change immediately since the sponsor approved it
- Explain that all changes must follow the formal change control process (Correct answer)
- Escalate to senior management
- Reject the change outright
Correct answer: Explain that all changes must follow the formal change control process
Even sponsor-initiated changes must be processed through formal change control to assess impact and maintain baseline integrity.
Question 2: Which of the following is an example of a preventive action in the context of change control?
- Correcting a defect discovered during testing
- Updating the risk register after a risk occurs
- Adjusting the project schedule to avoid a future delay (Correct answer)
- Submitting a change request for added scope
Correct answer: Adjusting the project schedule to avoid a future delay
A preventive action is taken proactively to reduce the probability of negative consequences before they occur.
Question 3: What distinguishes a defect repair from a corrective action?
- Defect repair addresses a non-conforming product; corrective action re-aligns future work with the plan (Correct answer)
- Corrective action is performed during planning; defect repair during closing
- Both terms are interchangeable in PMBOK
- Defect repair requires CCB approval; corrective action does not
Correct answer: Defect repair addresses a non-conforming product; corrective action re-aligns future work with the plan
Defect repair fixes a specific non-conforming component, while a corrective action aligns future project performance with the project management plan.
Question 4: During a configuration audit, the team discovers that a delivered software module does not match its approved design specification. This finding is called a:
- Change request
- Configuration discrepancy (Correct answer)
- Defect
- Variance
Correct answer: Configuration discrepancy
A configuration discrepancy (also called a configuration audit finding) is any difference between the configuration item and its documented requirements.
Question 5: Which input is MOST important when evaluating the impact of a proposed change?
- Stakeholder register
- Project management plan (Correct answer)
- Work performance reports
- Lessons learned register
Correct answer: Project management plan
The project management plan contains all baselines and subsidiary plans needed to assess how a proposed change will affect scope, schedule, cost, and quality.
Question 6: A project team is using a version control system to manage project documents. This practice is BEST associated with:
- Risk management
- Configuration management (Correct answer)
- Quality management
- Communications management
Correct answer: Configuration management
Version control is a core configuration management practice that tracks changes to documents and ensures teams work from current, approved versions.
Question 7: When should a change request be formally documented?
- Only when the change impacts the project budget
- Whenever any change to any project document is proposed (Correct answer)
- Only for changes that affect the scope baseline
- When the change is approved by the project sponsor
Correct answer: Whenever any change to any project document is proposed
All proposed changes—regardless of size or impact—should be formally documented as change requests so they can be tracked and controlled.
A sponsor requests an urgent feature addition without going through the change control process.
What should the project manager do?