Change Control & Configuration Flashcards

7 cards from real CAPM practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Change Control & Configuration flashcards as text
  1. A sponsor requests an urgent feature addition without going through the change control process. What should the project manager do?

    Answer: Explain that all changes must follow the formal change control process

    Even sponsor-initiated changes must be processed through formal change control to assess impact and maintain baseline integrity.

  2. Which of the following is an example of a preventive action in the context of change control?

    Answer: Adjusting the project schedule to avoid a future delay

    A preventive action is taken proactively to reduce the probability of negative consequences before they occur.

  3. What distinguishes a defect repair from a corrective action?

    Answer: Defect repair addresses a non-conforming product; corrective action re-aligns future work with the plan

    Defect repair fixes a specific non-conforming component, while a corrective action aligns future project performance with the project management plan.

  4. During a configuration audit, the team discovers that a delivered software module does not match its approved design specification. This finding is called a:

    Answer: Configuration discrepancy

    A configuration discrepancy (also called a configuration audit finding) is any difference between the configuration item and its documented requirements.

  5. Which input is MOST important when evaluating the impact of a proposed change?

    Answer: Project management plan

    The project management plan contains all baselines and subsidiary plans needed to assess how a proposed change will affect scope, schedule, cost, and quality.

  6. A project team is using a version control system to manage project documents. This practice is BEST associated with:

    Answer: Configuration management

    Version control is a core configuration management practice that tracks changes to documents and ensures teams work from current, approved versions.

  7. When should a change request be formally documented?

    Answer: Whenever any change to any project document is proposed

    All proposed changes—regardless of size or impact—should be formally documented as change requests so they can be tracked and controlled.