A requirements baseline has been approved. A stakeholder later requests a change. What process should the business analyst follow?
-
A
Add the change immediately to keep stakeholders happy
-
B
Reject the change to protect the baseline
-
C
Submit the change through the formal change control process
-
D
Document the change and implement it after the project closes