CAPM Cost & Schedule Management Flashcards
6 cards from real CAPM practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 6 CAPM Cost & Schedule Management flashcards as text
Fast tracking as a schedule compression technique involves:
Answer: Performing activities in parallel that were originally planned in sequence
Fast tracking overlaps activities that would normally be done sequentially, reducing overall duration but increasing risk of rework.
What does the Estimate at Completion (EAC) represent in Earned Value Management?
Answer: The expected total cost of the project when it is finished
EAC is the expected total cost of completing all project work, calculated by combining actual costs to date with an estimate for the remaining work.
In project scheduling, what is the difference between a mandatory dependency and a discretionary dependency?
Answer: Mandatory dependencies are legally or contractually required; discretionary are preferred sequencing choices
Mandatory dependencies are inherent in the nature of work or required by contract/law (hard logic), while discretionary dependencies reflect preferred or best-practice sequencing (soft logic).
Which type of cost is incurred regardless of project output, such as executive salaries and facility leases?
Answer: Fixed cost
Fixed costs do not change based on project output or work volume, such as rent, salaries of permanent staff, or equipment lease fees.
What is a contingency reserve in project cost management?
Answer: Budget allocated to handle identified risks with known probability and impact
Contingency reserves are budget amounts added to the cost estimate to account for identified risks (known unknowns) and are part of the cost baseline.
Which scheduling output represents the planned dates for starting and finishing project activities?
Answer: Project schedule baseline
The project schedule baseline is the approved version of the schedule model, showing planned start and finish dates for activities, used to measure schedule performance.