In a Capital One assessment scenario, your team's project is two weeks behind schedule and the deadline is fixed. What is the BEST first action?
-
A
Work overtime independently without informing your manager
-
B
Immediately escalate to your manager with a root cause analysis and proposed recovery plan
-
C
Reduce the quality of deliverables to meet the deadline
-
D
Request the deadline be extended without offering alternatives