A quality team applies a risk matrix and finds a nonconformance in the 'intolerable' zone. What is the required immediate response?
-
A
Stop the process or quarantine affected product and initiate urgent CAPA
-
B
Document and schedule for the next quarterly review
-
C
Notify customers without stopping production
-
D
Reduce the risk rating through consensus and continue