During the business problem framing stage of a CAP analytics project, what is the primary purpose of a risk register?
-
A
To track the budget spent on data acquisition activities
-
B
To record all stakeholder contact information for the project
-
C
To list the software licenses required for model deployment
-
D
To document identified risks, their likelihood, impact, and planned responses