A control account's Schedule Performance Index (SPI) is 1.15. What does this indicate?
-
A
The project is 15% over budget
-
B
The project is accomplishing 15% more work than planned for time elapsed
-
C
The project is 15% behind schedule
-
D
The project will complete 15% late