CAM Cheat Sheet 2026

The 30 highest-yield CAM facts, distilled from real exam questions. Print it, save it as a PDF, or study it here โ€” free, no sign-up.

100 questions
90 min time limit
70.00% to pass
  1. Which condition requires a variance analysis report (VAR) from a Control Account Manager? โ†’ A cost or schedule variance exceeds established thresholds
  2. During execution, a CAM wants to change the earned value method on an in-progress work package to improve reported performance. This is: โ†’ Prohibited, because changing methods on open work distorts performance measurement
  3. A work package planned as level of effort (LOE) will always show what schedule variance? โ†’ Zero, because BCWP always equals BCWS
  4. What distinguishes an 'issue' from a 'risk' in program management terminology? โ†’ An issue has already occurred, while a risk is a potential future event
  5. In risk-adjusted scheduling, what is 'schedule margin'? โ†’ A designated buffer of time placed before key events to protect against schedule risk
  6. Actual costs in a control account should be recorded in a manner consistent with which other element? โ†’ The way the corresponding budget was planned and earned value is claimed
  7. Under EIA-748, work authorization documents must exist before work begins primarily to ensure that: โ†’ All effort is tied to authorized scope, schedule, and budget with clear responsibility
  8. A work package has PV of $60,000, EV of $45,000, and AC of $50,000. What are the cost and schedule variances? โ†’ CV = โˆ’$5,000 and SV = โˆ’$15,000
  9. A CAM leaving the company is asked by their new employer to bring copies of control account plans. Taking them would be: โ†’ A breach of confidentiality and misappropriation of proprietary information
  10. In variance analysis and risk response, a 'workaround' is best defined as: โ†’ A response to a risk event that was not previously identified in the risk register
  11. Management reserve may properly be used to: โ†’ Budget newly identified in-scope work arising from realized risks
  12. In an EVM toolset, actual costs typically flow into the cost engine from which source system? โ†’ The corporate accounting or ERP system
  13. Which file-based mechanism is commonly used to move monthly performance data between a contractor's EVM system and government analysis tools? โ†’ Standardized electronic data formats such as the IPMDAR JSON/XML datasets
  14. Which risk response strategy involves transferring risk responsibility to a third party? โ†’ Risk transfer
  15. A teammate asks a CAM to sign off on completed work the CAM has not verified. The CAM should: โ†’ Verify the work personally or through objective evidence before signing
  16. Which entity audits contractor accounting systems and incurred costs supporting EVMS data on government contracts? โ†’ Defense Contract Audit Agency (DCAA)
  17. What does a Schedule Performance Index (SPI) value less than 1 indicate? โ†’ Project is behind schedule
  18. Which document formally conveys scope, schedule, and budget authority to a CAM? โ†’ The work authorization document
  19. Which element ties a control account to the responsible organizational unit, ensuring single-point accountability? โ†’ The intersection of the WBS and the organizational breakdown structure (OBS)
  20. Which of the following is a key element of maintaining data integrity in earned value management? โ†’ Ensuring performance is claimed only per pre-defined earning rules
  21. Freezing changes to budgets and earned value within the current accounting period primarily protects what? โ†’ The integrity of current-period performance measurement
  22. A control account with a $400,000 BAC is 60% complete with ACWP of $270,000. What is the cost variance? โ†’ -$30,000
  23. A customer representative privately asks a CAM to share a competitor's pricing data seen during a prior engagement. The CAM should: โ†’ Refuse, as sharing it would violate procurement integrity and confidentiality rules
  24. A CAM is asked by a program manager to set earned value equal to actual costs to eliminate a cost variance. What should the CAM do? โ†’ Refuse, because manipulating earned value violates EVMS integrity requirements
  25. What is a fundamental principle of Foundational Concepts & Principles in Control Account Manager Certification practice? โ†’ Following established standards and best practices
  26. A CAM needs to add newly authorized in-scope work to a control account. Which is the correct source of budget? โ†’ Undistributed budget allocated through a formal budget change request
  27. A control account shows SV = โˆ’$50,000 but the tasks driving it have large total float. How should the CAM characterize the schedule impact? โ†’ Unfavorable earned value schedule variance with no immediate critical-path impact
  28. What is the role of a code of conduct in Control Account Manager Certification practice? โ†’ It establishes expected behavioral and professional standards
  29. When schedule performance is also expected to affect future costs, which EAC approach is most appropriate? โ†’ EAC = AC + (BAC โˆ’ EV) รท (CPI ร— SPI)
  30. A CAM sees repeated favorable cost variances caused by front-loaded budget in early work packages. What EVMS risk does this create? โ†’ A rubber baseline that masks true performance and defers problems to later periods
Was this helpful?