CAM Cheat Sheet 2026
The 30 highest-yield CAM facts, distilled from real exam questions. Print it, save it as a PDF, or study it here โ free, no sign-up.
100 questions
90 min time limit
70.00% to pass
- Which condition requires a variance analysis report (VAR) from a Control Account Manager? โ A cost or schedule variance exceeds established thresholds
- During execution, a CAM wants to change the earned value method on an in-progress work package to improve reported performance. This is: โ Prohibited, because changing methods on open work distorts performance measurement
- A work package planned as level of effort (LOE) will always show what schedule variance? โ Zero, because BCWP always equals BCWS
- What distinguishes an 'issue' from a 'risk' in program management terminology? โ An issue has already occurred, while a risk is a potential future event
- In risk-adjusted scheduling, what is 'schedule margin'? โ A designated buffer of time placed before key events to protect against schedule risk
- Actual costs in a control account should be recorded in a manner consistent with which other element? โ The way the corresponding budget was planned and earned value is claimed
- Under EIA-748, work authorization documents must exist before work begins primarily to ensure that: โ All effort is tied to authorized scope, schedule, and budget with clear responsibility
- A work package has PV of $60,000, EV of $45,000, and AC of $50,000. What are the cost and schedule variances? โ CV = โ$5,000 and SV = โ$15,000
- A CAM leaving the company is asked by their new employer to bring copies of control account plans. Taking them would be: โ A breach of confidentiality and misappropriation of proprietary information
- In variance analysis and risk response, a 'workaround' is best defined as: โ A response to a risk event that was not previously identified in the risk register
- Management reserve may properly be used to: โ Budget newly identified in-scope work arising from realized risks
- In an EVM toolset, actual costs typically flow into the cost engine from which source system? โ The corporate accounting or ERP system
- Which file-based mechanism is commonly used to move monthly performance data between a contractor's EVM system and government analysis tools? โ Standardized electronic data formats such as the IPMDAR JSON/XML datasets
- Which risk response strategy involves transferring risk responsibility to a third party? โ Risk transfer
- A teammate asks a CAM to sign off on completed work the CAM has not verified. The CAM should: โ Verify the work personally or through objective evidence before signing
- Which entity audits contractor accounting systems and incurred costs supporting EVMS data on government contracts? โ Defense Contract Audit Agency (DCAA)
- What does a Schedule Performance Index (SPI) value less than 1 indicate? โ Project is behind schedule
- Which document formally conveys scope, schedule, and budget authority to a CAM? โ The work authorization document
- Which element ties a control account to the responsible organizational unit, ensuring single-point accountability? โ The intersection of the WBS and the organizational breakdown structure (OBS)
- Which of the following is a key element of maintaining data integrity in earned value management? โ Ensuring performance is claimed only per pre-defined earning rules
- Freezing changes to budgets and earned value within the current accounting period primarily protects what? โ The integrity of current-period performance measurement
- A control account with a $400,000 BAC is 60% complete with ACWP of $270,000. What is the cost variance? โ -$30,000
- A customer representative privately asks a CAM to share a competitor's pricing data seen during a prior engagement. The CAM should: โ Refuse, as sharing it would violate procurement integrity and confidentiality rules
- A CAM is asked by a program manager to set earned value equal to actual costs to eliminate a cost variance. What should the CAM do? โ Refuse, because manipulating earned value violates EVMS integrity requirements
- What is a fundamental principle of Foundational Concepts & Principles in Control Account Manager Certification practice? โ Following established standards and best practices
- A CAM needs to add newly authorized in-scope work to a control account. Which is the correct source of budget? โ Undistributed budget allocated through a formal budget change request
- A control account shows SV = โ$50,000 but the tasks driving it have large total float. How should the CAM characterize the schedule impact? โ Unfavorable earned value schedule variance with no immediate critical-path impact
- What is the role of a code of conduct in Control Account Manager Certification practice? โ It establishes expected behavioral and professional standards
- When schedule performance is also expected to affect future costs, which EAC approach is most appropriate? โ EAC = AC + (BAC โ EV) รท (CPI ร SPI)
- A CAM sees repeated favorable cost variances caused by front-loaded budget in early work packages. What EVMS risk does this create? โ A rubber baseline that masks true performance and defers problems to later periods
Turn these facts into recall:
Was this helpful?