A CAM's control account shows a favorable cost variance, but the risk register lists an unmitigated technical risk in a future work package. How should the CAM report status?
-
A
Report the favorable variance and explicitly note the open risk to future performance in the variance analysis
-
B
Report only the favorable variance since risks are the risk manager's job
-
C
Offset the favorable variance against the risk exposure and report zero variance
-
D
Delay reporting until the risk is retired