A Control Account Manager identifies a supplier delay that could impact a critical milestone. What is the FIRST action the CAM should take?
-
A
Document the risk in the project risk register and assess its probability and impact
-
B
Immediately reallocate management reserve to cover the delay
-
C
Rebaseline the control account to absorb the schedule slip
-
D
Wait until the variance exceeds thresholds before reporting