A surveillance team samples a CAM's estimate at completion (EAC) and finds it has not changed in twelve months despite a steadily worsening cost performance index. What quality deficiency does this indicate?
-
A
The EAC is not being updated based on current performance data, undermining its validity
-
B
The management reserve is too small
-
C
The schedule baseline lacks a critical path
-
D
The CAM is using too many work packages