A CAM's control account shows a cumulative cost variance of -$50,000 that exceeds the reporting threshold. What integrated action is required?
-
A
Prepare a variance analysis report explaining cause, impact, and corrective action
-
B
Wait to see whether the variance self-corrects next month
-
C
Rebaseline the control account to zero out the variance
-
D
Shift budget from management reserve to close the gap