A Control Account Manager discovers that a scope change approved by the customer has not yet been reflected in the performance measurement baseline. What should the CAM do first?
-
A
Process the change through the formal baseline change control process
-
B
Begin work on the new scope immediately to avoid schedule delays
-
C
Adjust the control account budget informally and document it later
-
D
Report the variance as unfavorable until the contract ends