A CAM is asked by a program manager to set earned value equal to actual costs to eliminate a cost variance. What should the CAM do?
-
A
Refuse, because manipulating earned value violates EVMS integrity requirements
-
B
Comply, since the program manager has authority over the baseline
-
C
Comply, but only for one reporting period
-
D
Transfer the variance to management reserve