A subcontractor performs 30% of a control account's discrete work. How should the CAM incorporate the subcontractor's performance?
-
A
Exclude subcontract effort from earned value entirely
-
B
Report subcontract cost as level of effort regardless of work type
-
C
Integrate subcontractor earned value data into the control account consistent with the EVMS
-
D
Claim 100% earned value when the subcontract is signed