A CAM needs to add newly authorized in-scope work to a control account. Which is the correct source of budget?
-
A
Undistributed budget allocated through a formal budget change request
-
B
Borrowing budget from a future work package without documentation
-
C
Reducing the fee to fund the new work
-
D
Increasing EV to cover the added scope