A CAM's control account shows a favorable cost variance caused by delayed material deliveries. How should this be communicated?
-
A
Document that the favorable variance is timing-related and flag the future cost and schedule impact
-
B
Report it as pure savings with no further explanation
-
C
Hide the variance since it is favorable
-
D
Transfer the budget to another account immediately