A CAM notices a control account's cumulative CPI is 0.85 while the SPI is 1.05. What does this combination most likely indicate?
-
A
Work is ahead of schedule but costing more than planned
-
B
Work is behind schedule and under budget
-
C
The performance measurement baseline is corrupt
-
D
Management reserve has been depleted