What is 'labor rate variance' in CAM resource management?
-
A
The difference between planned and actual hours worked
-
B
The difference between the planned and actual cost per hour for labor resources
-
C
The variance caused by rework on labor-intensive tasks
-
D
The cost difference between direct and indirect labor