During sprint planning, the team realizes the top-priority backlog item is too large to complete in one sprint. What is the BEST course of action?
-
A
Skip the item and move to the next priority
-
B
Break the item into smaller stories that fit within the sprint
-
C
Extend the sprint length to accommodate the item
-
D
Assign the item to the most senior developer only