A Product Owner wants to cancel a Sprint. Under what condition is this allowed in Scrum?
-
A
When the Developers are underperforming
-
B
When the Sprint Goal becomes obsolete
-
C
When the Sprint is more than halfway complete
-
D
When the Scrum Master recommends it