During a Sprint Review, a stakeholder requests a major feature change that wasn't in the original Sprint Goal. What should the Scrum Team do?
-
A
Add it to the current Sprint immediately
-
B
Note the feedback and add it to the Product Backlog for future consideration
-
C
Reject the request since the Sprint is already underway
-
D
Extend the Sprint to accommodate the new feature