A team is midway through a sprint when the Product Owner realizes a higher-priority item was overlooked. What should the Product Owner do?
-
A
Immediately replace a sprint backlog item with the new item
-
B
Add the item to the product backlog and prioritize it for the next sprint
-
C
Cancel the sprint and restart planning
-
D
Ask the Scrum Master to pause the current sprint